Changes effective: January 22nd, 2025
Version: 2.1
New Features/Enhancements
- User Defined Blocking
- The ability to change waste or an offcut into blocking to be shipped with a project.
- The user would click to "convert" the piece to blocking.
- The user will select which project the block will belong to.
- The new blocking piece is then created and the project information is identified in the mouseover notation.
- Edit Offcut – Split Offcut
- Allow the user to split an offcut into two pieces from a specified length.
- The user would click "Split" from the blocking dropdown.
- The user would use the Length Dropdown to pick the desired offcut length.
- The dropdown will only list lengths between the set Min Offcut length and the total length of the original offcut.
- The user makes a selection and the original piece is updated to show the two new lengths.
Bug Fixes
- Display Issue After Edit Cut (Hundegger)
- Fixed an issue that occurred when moving a grouped cut and the offcut or waste was not last.
- Distribution group numbers not updating when adding material list to Batch
- Add logic to delete the distribution group settings when adding a material list and the distribution group is set to Per Project or Per Level. This forces a rebuild downstream.
- Edit cut list text display issue
- Fix to show full board length text on edit cut list screen. This also means offcuts will show actual length.
- If Maximum waste is not set, Minimum offcut value is used
- This reduces the likelihood of a user creating a less than 1’ offcut on the edit cut list screen.
- Product mapping issue with Material List import
- Added some additional logging. No changes for encoding issue.